TBTE Engineering is scheduled to begin roadway core drilling this week (tentative start date Tuesday) for geotechnical data for the road rehab design work planned for Stevens, Spruce, Howe as part of the Town of Marathon Road Asset Management plan for future roadway rehabilitation.

Attached marked plans for reference, with sewers to be inspected, minimal disruption will take place.

  • Stevens Avenue, Storm and Sanitary Sewer
  • Howe Street, Storm and Sanitary Sewer
  • Spruce Ct., Sanitary Sewer

Proposed Road Rehab Sections :

  1. Stevens Avenue - Between Trailer Park Street and Peninsula Road (approximately road length 1.10 km)
  2. Howe Street – Between Pebble Beach and Yawkey Avenue (approximately road length 0.21 km)
  3. Spruce Ct. – Between Aspendale Drive and Sund Crescent (approximately road length 0.18 km)